PanelFoundry's Phase 1 features: what each one does, what it means for Modutec's engineers, estimators and distributors, and how far along it is. Below them are the journey from the MODDIS catalogue to a distributor's quotation, the work stage by stage, and the task list between Modutec and PanelFoundry. It is built on the points Mr. Ramani and the team raised in our meetings.

Document
Phase 1 features and status
Revision
16 Oct 2026
Distribution
Confidential, Modutec only
Access
Modutec on PanelFoundry's production platform: target 13 November 2026, earlier if ready
Testing
Modutec's own team tests first, then a distributor
Go-live
Target: 1 January 2027
Exhibition
ELECRAMA, end of January 2027
Hosted
Mumbai, India (from 13 November)

What PanelFoundry gives you

Done Built, being checked Being built Planned

The customer journey, end to end

From Modutec's catalogue to the quotation a distributor hands its customer. Each step names the stage that delivers it and where that stage stands. Automatic layout from the single-line comes in a later phase, as agreed in our meetings.

The work, stage by stage

StageProgressPieces of workTarget

Tasks between Modutec and PanelFoundry

What we need from Modutec, in the depth Mr. Ramani asked for on 15 October, and what PanelFoundry owes Modutec: an owner, a co-owner, a target and remarks for each task. On Modutec's tasks the target is the date PanelFoundry needs the item by, until Rakesh's own task list confirms or moves it; on PanelFoundry's it is the date we deliver by. None of Modutec's tasks stops the work: until each arrives, PanelFoundry says plainly what is waiting on Modutec, and design carries on.

#TaskOwnerCo-ownerTargetRemarks